Five research chambers, retrofitted in place, one at a time.

Refrigeration for the environmental chamber retrofit in the Nanaline Duke Building at Duke University Medical Center. The project is ongoing; this page is updated as milestones are reached.

Project overview.

Customer
Duke University Medical Center
Location
Durham, NC
Scope
Five research environmental chambers
Operating range
4 °C to 40 °C
Status
In progress
Last updated
5 September 2026

Five research chambers in the Nanaline Duke Building serve active laboratory programs. Each is being rebuilt in place rather than replaced, one at a time, so the labs around it keep working. When each is done it will hold any temperature from 4 °C to 40 °C.

3C is the refrigeration contractor on the project, working alongside Duke’s facilities and engineering teams and under the general contractor’s phased move-out and move-in schedule.

Scope.

What each chamber gets from 3C.

  • A new refrigeration system for each chamber, sized to that chamber rather than a one-size install
  • Protection so the compressor survives a hard pull-down from 40 °C or a warm start after a move-in
  • Hot gas bypass for fine temperature control through the middle of the range, and electric heat to hold the top of it
  • Desiccant dehumidification in every chamber, with two units in the chamber that carries the heaviest moisture load
  • Hot gas defrost, so the chambers hold temperature without a manual defrost interrupting a program

Engineering challenges.

  1. The building's condenser water is cold.Cold enough to drag the system's pressure below what its valves need to work. Each unit regulates its own water flow to hold a minimum pressure, and we set that flow from the manufacturer's tables rather than a default.
  2. The drawings needed correcting.Our review found a protection valve placed on the wrong side of another component and a defrost valve that would have flooded the compressor. We documented each item, redlined the drawing, and settled it with Duke's engineering team before building.
  3. One line was marginal on paper.The lead chamber's liquid line came out borderline in the engineering review. Rather than add equipment to be safe, we agreed with Duke to test it at commissioning and add the fix only if the test calls for it.
  4. One chamber had more moisture than one unit could handle.Chamber 224CR got two dehumidifiers instead of one, wired to alternate weekly and to alarm if either fails, with ducting that kept new penetrations through the chamber wall to two.

Approach.

A retrofit means working inside walls, openings, and building utilities that were never designed around the new equipment.

So every selection on this project is checked against what is actually on site before parts are ordered. Where the drawings and the building disagreed, we wrote the difference down and settled it with Duke’s engineering team instead of building to an unverified number.

Status.

  1. 5 September 2026

    • Chamber 140CR, the lead chamber, is in the final stage of our scope. Its commissioning results will set the baseline for the remaining four.
    • The added dehumidification for chamber 224CR is complete and approved.
    • The schedule for the remaining four chambers is expected to shift later, pending the general contractor's confirmation.

Next update.

  • 140CR commissioning results
  • Corrected drawings released

Installments are added here as milestones are reached. Customer names appear only with permission.